|
The first important thing to consider is will remain in your home or
move out for the duration of the project. If your project involves
any substantial remodeling of existing spaces, I urge you to move to
temporary quarters. What do I mean by substantial? Well if it is
anything more than painting or floor coverings, the work is
substantial. Work that involves moving walls, reworking electrical,
plumbing or mechanical systems can make your home unlivable. Rent
the movie “The Money Pit” and see what I mean. On the other hand, if
you are having an addition to your home, you may be able to remain
and not be overly affected by the work. You should discuss your
options with your architect/designer early on in the project.
If you are going to vacate, then move all your belongings out of the
areas of work to a secure location. With the contractor in full
control of your property, you don’t want things to disappear. You
also may realize some savings since the contractor will know his
workflow will be uninterrupted.
Permits
A building permit is generally required whenever structural work is
involved or when the basic living area of a home is to be changed.
To be sure, check your local requirements. If your contract does not
provide that the contractor will obtain the permits and he doesn't,
you may be held legally responsible.
Do not get any permit yourself. If you do, you will be considered to
be the contractor, and you could be held liable if the work does not
comply with the building codes.
Notice to Proceed
Prior to starting work, you should issue a formal "Notice to
Proceed". This will serve to document the official start date for
the project and will define the agreed completion date. This is
important for several reasons. First the dates of start and
completion are clearly spelled out. Second, many states have time
limitations on when Liens can be filed based on those dates. Third,
it lets the contractor know you will be monitoring his progress. You
don’t want to have to be asking the contractor when he will be done
and his answer every time is "two weeks".
Schedule of Values
Most standard construction contracts require the contractor to
furnish you with a Schedule of Values. The Schedule of Values is a
detailed statement furnished by the contractor, builder or others
outlining the portions of the contract sum. It allocates values for
the various parts of the work and is also used as the basis for
submitting and reviewing progress payments.
The schedule will be broken down by the major steps in the project
making it easy to monitor the progress of the job as well as
validate applications for payment. For example, the schedule of
values allows $2000 for interior doors. The contractor submits a
payment application that includes $2000 for interior doors. If the
inspection shows all the interior doors are in place, the contractor
is entitled to full payment for the interior doors. If the
inspection shows half the interior doors are in place, the
contractor is only entitled to 50% or $1000 on the current payment
application.
Monitor progress daily
During the course of the work, it is important you visit the work
area on a daily basis. The best time is after working hours. This
way you can see if the contractor is proceeding in a timely manner.
This daily monitoring can alert you early on to potential problems
the contractor may have being able to man the job or pay for
materials.
Take photos
There is no better way to document progress and problems than by
taking photos and lots of them. I suggest you buy a digital camera
if you don’t have one and use it every time you visit the site.
Payments
First, on the subject of down payments, my advice to you is making a
down payment weakens your position. A qualified contractor should
have sufficient resources to fund the construction of the job
without advances.
The frequency of progress payment should be defined in the contract
usually weekly, bi-weekly or monthly. When the contractor submits
his application for payment, the site should be visited and the
application verified against the actual work performed. Here is
another instance when having an architect on your team pays many
times over. An architect will visit the site, verify the work in
place and provide you with a written report. He will also certify
the application for payment. With this paperwork in hand you can
feel confident the contractor is not being paid for work in advance.
On a personal note, the very first job I monitored early in my
career the contractor submitted a payment application with a huge
advance he said was for materials he had ordered. I refused to
certify the payment. We later found out he was trying to scrape
together enough money to pay for his Colorado deer hunting trip the
next week!
Retainage
Retainage is another issue to be considered during the contract
negotiations and is an important safeguard for you as owner. I
recommend 10% be withheld from every payment application. Your
architect can advise you on this. The purpose of retainage is simply
to keep the contractor interested in finishing the project. There is
an old saying in construction that “the last 5% of a job is the
hardest to complete”. By the time your project is 95% complete, the
contractor has likely started another job. His attention is
naturally focused on the job that will make him the most money for
that current month. Having an extra 10% keeps him interested in
completing your job.
The final payment including retainage is normally not approved until
all work has been inspected, all paperwork is turned in and any
requirements of local building officials have been completed.
Protect yourself
Once the work begins, if your contractor will have to use
subcontractors, you should protect yourself from liens against your
home in the event the primary contractor doesn't pay the
subcontractors or suppliers. You can do this by insisting upon a
lien release from all subcontractors and suppliers before you pay
for any work. Or, you can use the services of a construction control
company. For a small percentage of your contract price, you may
deposit your payments with them and they will disburse the funds and
secure the lien releases for you. Although they are not required to
inspect the work, they generally do.
Inspections
Inspections will occur throughout the project. There will be local
required inspections performed by the local building officials.
Additional inspections will be performed to certify payment
applications and to monitor the progress of the work.
Change Orders
Even with the best plans and specifications, sometimes hidden
conditions will be uncovered that will require a change order. These
conditions can range from problems with the soils on your site to
uncovered substandard construction that must be brought into
compliance with current codes. For too many contractors, this is
where they plan to make their money by bidding low to get the job
and then hitting you with a flurry of inflated change orders. Your
architect will assist you in validating any change orders
negotiating a true and fair cost.
Also be aware, if you decide to make changes during the course of
the work because you don’t like something or want a different
material, you will receive a change order and the price will be much
higher than if you made the change during the planning stage. Again,
proper planning will eliminate or minimize these costly change
orders. It is not unusual for a poorly planned project to double in
price during construction.
To learn more tips on your home remodeling project or new
construction, go to here.
My name is Frank Orts and I have been in the design
and construction business for close to 30 years. I have my own
architecture practice and have owned my own construction company. In
all those years, I have been most concerned that my clients received
the most value for their money delivered in a fair way. Visit my
blog at
http://www.frugalarchitect.com
Article Source:
http://EzineArticles.com/?expert=Frank_Orts
If you are looking for a professional remodeling contractor in Santa
Cruz County then, please call us at
831-246-0555
or
complete our online form.
|